sitemap | Font size: default text size - Change text size to medium - Change text size to large
 
 
 
 

Latest news

February 2008

World first for Korean immersed tunnel

A Daewoo Engineering and Construction led contractor consortium has successfully placed the first 45,000 tonnes by 180m long element of South Korea’s first ever immersed tunnel. Halcrow working in joint venture with Tunnel Engineering Consultants of the Netherlands is technical consultant to the main contractor.

The 8.2km long $5.8 billion Busan - Geoje Fixed Link Project includes a 3.2km undersea roadway tunnel that goes far beyond today’s common practice within concrete immersed tunnel technology. Key vital statistics:

the world’s deepest immersed roadway tunnel at 48m below mean water level and the world’s second longest immersed concrete tunnel
the site is exposed to severe open sea marine conditions from the Pacific Ocean
weak subsoil has required extensive soil improvement works
the tunnel is above the sea bed at both ends of the alignment
to accommodate swell wave conditions the immersion equipment is the largest ever used
immersion works have to be in a short weather window out-with the typhoon season
provision for seismic loading is included in the design giving special construction challenges
double watertight seals are provided at segment joints for the first time
two wider elements with climbing lanes will be used at one end, each weighing 48,000 tonnes
pre-cast concrete blocks up to 75 tonnes each protect the elements and artificial island entrances
the project is a public private partnership with 72% private and 28% government funding and a 40 year concession period
placing of element two is planned for early March 08
the link is scheduled to open to traffic before the end of 2010.

Each of the 18 elements consist of eight, 22.5m long concrete segments of cross section 26.46m wide by 9.97m high, with two dual carriageway roadway bores and a central gallery. Each segment is cast in full cross section and four elements are built at a time in a purpose built dry dock facility. After storing and fitting out at a temporary mooring area, the elements are towed 35km to the alignment and immersed by specialist sub-contractor Mergor Underwater

Engineering of the Netherlands.

The permanent works design is by a joint venture of COWI of Denmark and Daewoo Engineering.


Return to: latest news...

 

 

Halcrow news

Halcrow news

 
Busan - Geoje Fixed Link, courtesy of Peter de Haas
subscribe to RSS feed
To learn about RSS, click here