The Arrowhead Tunnels project forms part of California's Inland Feeder project, which is a critical component of a water transfer and storage system enabling the delivery of an additional 2.4 million cubic meters of water a day.
The segmental
linings for the Arrowhead east
and west tunnels are to be
constructed behind pressure
balance tunnel boring
machines to form 4.88m
internal diameter tunnels,
within which steel and
concrete pipes will be
constructed to form the
permanent works.
key factors:
 |
bolted and gasketed segmental tunnel lining |
 |
over 300m design external water pressure |
 |
high load on radial joints |
 |
testing regimes for gaskets and radial joints |
 |
design and build |
Halcrow undertook the
detailed design of the
segmental lining for the tunnel
sub-contractor,
Traylor-Shea-Ghazi, who
worked for main contractor
Shea-Kenny.
The bolted and
gasketed lining consisted of 5
segments plus a key and had
a structural thickness of
330mm, with straight "spear"
bolts through both radial and
circumferential joints.
The
design was developed using
two different concrete
strengths to suit the varying
loads within the tunnel drives
(approximately 50MPa and
65MPa cube strength). The
segments were reinforced and
particular attention was given
to the radial joints where high
stresses meant an onerous
design situation had to be
economically accommodated.
A special lining was also
developed that allowed the
use of a grout bag on the
outside of the lining, to form
an external seal between the
lining and the rock in areas of
high water flow.
|