Black Hill Tunnel - Hong Kong  
 

Black Hill tunnel

client:
..
Dumez-GTM-Chun Wo Joint Venture
 
 
country:
..
China
 
 
year:
..
 
 

Halcrow was appointed as the detailed design consultant by the Dumez-GTM-Chun Wo Joint Venture for the design of four 6 m diameter rock tunnels with a total length in excess of 9 km, and associated shafts, adits, central siding and crossover tunnels and portals.

The tunnels pass under Black Hill between Yau Tong and Tiu Keng Leng station and form part of the Tsuen Kwan O Extension Project for the Hong Kong Mass Transit Railway.

9 km of railway tunnel in rock
Rock tunnel design (drill-and-blast)
Mass concrete linings with waterproof membrane
Multiple tunnels with crossovers and sidings
Cut-and cover tunnel structures
Design and build project
Geotechnical and hydrogeological interpretation
Tunnel drainage and pump system design
System assurance studies
Site design liaison