sitemap | Font size: default text size - Change text size to medium - Change text size to large
 
 
 
 
Back button. Return to previous page
 
Busan Geoje Fixed Link Project  
 

Busan Geoje Fixed Link Project

client:
..
South Korea
 
 
country:
..
Daewoo Engineering and Construction Co., Ltd
 
 
year:
..
2003 - ongoing
 
 

Scope:

Busan Geoje Fixed Link Project, comprising two cable stayed bridges and an immersed tube tunnel, will provide an 8.2km highway link between the southern city of Busan and the island of Geoje in South Korea.

Technical Adviser, Design and Constrution of major bridges, cable stayed bridges, immersed tube tunnels, Contracts advice.

Key factors :

Main cable stayed bridge with 475m main span
Secondary cable stayed bridge with twin 230m main spans
Associated viaducts
3.4km long immersed tunnel in 40m depth of water
Technical Adviser to Concession Company/constructor
Design and construction advice
Contracts advice
Heavy marine foundations