In the ongoing development of the deepwater port at Hamriyah, Sharjah Ports Authority commissioned the development of additional berths and backup facilities to cater for general cargo vessels and potential post-panamax container vessels.
scope
 |
concept design |
 |
preliminary design and budget preparation |
 |
detailed design |
 |
tender documents |
 |
contract supervision |
benefit to clients
 |
demolition of piled pontoon
berth |
 |
removal of precast concrete mat armoured slope protection |
 |
240m -14.0m general cargo berth |
 |
645m -16.0m container berths |
 |
610m piled crane beam for 80t gantry crane |
 |
dredging to be completed later |
|